TY - GEN
T1 - The SNS machine protection system
T2 - Particle Accelerator Conference, PAC 2005
AU - Sibley, C.
AU - Armstrong, D.
AU - Jones, A.
AU - Justice, A.
AU - Thompson, D.
PY - 2005
Y1 - 2005
N2 - The Spallation Neutron Source under construction in Oak Ridge TN has commissioned low power beam up to 187 MeV. The number of MPS inputs is about 20% of the final number envisioned. Start-up problems, including noise and false trips, have largely been overcome by replacing copper with fiber and adding filters as required. Initial recovery time from Machine Protection System (MPS) trips was slow due to a hierarchy of latched inputs in the system: at the device level, at the MPS input layer, and at the operator interface level. By reprogramming the MPS FPGA such that all resets were at the input devices, MPS availability improved to acceptable levels. For early commissioning MPS inputs will be limited to beam line devices that will prohibit beam operation. For later operation, the number of MPS inputs will increase as both software alarms and less intrusive MPS inputs such as steering magnets are implemented. Two upgrades to SNS are on the horizon: a 4 MW upgrade and a second target station. Although these are years away the MPS system as designed should easily accommodate the increase in power and pulse-to-pulse target switching at 120 Hz.
AB - The Spallation Neutron Source under construction in Oak Ridge TN has commissioned low power beam up to 187 MeV. The number of MPS inputs is about 20% of the final number envisioned. Start-up problems, including noise and false trips, have largely been overcome by replacing copper with fiber and adding filters as required. Initial recovery time from Machine Protection System (MPS) trips was slow due to a hierarchy of latched inputs in the system: at the device level, at the MPS input layer, and at the operator interface level. By reprogramming the MPS FPGA such that all resets were at the input devices, MPS availability improved to acceptable levels. For early commissioning MPS inputs will be limited to beam line devices that will prohibit beam operation. For later operation, the number of MPS inputs will increase as both software alarms and less intrusive MPS inputs such as steering magnets are implemented. Two upgrades to SNS are on the horizon: a 4 MW upgrade and a second target station. Although these are years away the MPS system as designed should easily accommodate the increase in power and pulse-to-pulse target switching at 120 Hz.
UR - http://www.scopus.com/inward/record.url?scp=33847109451&partnerID=8YFLogxK
U2 - 10.1109/PAC.2005.1590892
DO - 10.1109/PAC.2005.1590892
M3 - Conference contribution
AN - SCOPUS:33847109451
SN - 0780388593
SN - 9780780388598
T3 - Proceedings of the IEEE Particle Accelerator Conference
SP - 1727
EP - 1729
BT - Proceedings of the Particle Accelerator Conference, PAC 2005
Y2 - 16 May 2005 through 20 May 2005
ER -