N2 - The Spallation Neutron Source (SNS) is under construction at Oak Ridge National Laboratory. The cold section of the Linac consists of 81 superconducting radio frequency cavities cooled to 2.1K by a 2400 watt cryogenic refrigeration system. The major cryogenic system components include warm helium compressors with associated oil removal and gas management, 4.5K cold box, 7000L liquid helium dewar, 2.1K cold box (consisting of 4 stages of cold compressors), gaseous helium storage, helium purification and gas impurity monitoring system, liquid nitrogen storage and the cryogenic distribution transfer line system. The overall system commissioning and future plans will be presented.
AB - The Spallation Neutron Source (SNS) is under construction at Oak Ridge National Laboratory. The cold section of the Linac consists of 81 superconducting radio frequency cavities cooled to 2.1K by a 2400 watt cryogenic refrigeration system. The major cryogenic system components include warm helium compressors with associated oil removal and gas management, 4.5K cold box, 7000L liquid helium dewar, 2.1K cold box (consisting of 4 stages of cold compressors), gaseous helium storage, helium purification and gas impurity monitoring system, liquid nitrogen storage and the cryogenic distribution transfer line system. The overall system commissioning and future plans will be presented.
KW - 2.1K cryogenic systems
KW - Accelerator technology
UR - http://www.scopus.com/inward/record.url?scp=33845408208&partnerID=8YFLogxK
U2 - 10.1063/1.2202566
DO - 10.1063/1.2202566
M3 - Conference contribution
AN - SCOPUS:33845408208
SN - 0735403171
SN - 9780735403178
T3 - AIP Conference Proceedings
SP - 1436
EP - 1443
BT - ADVANCES IN CRYOGENIC ENGINEERING
T2 - ADVANCES IN CRYOGENIC ENGINEERING: Transactions of the Cryogenic Engineering Conference, CEC
Y2 - 29 August 2005 through 2 September 2005
ER -