TY - JOUR
T1 - Process costing of the microchip
AU - Gopalakrishnan, Bhaskaran
AU - Gajera, Dipesh
AU - Gupta, Deepak P.
AU - Athinarayanan, Ragu
AU - Chaudhari, Subodh A.
PY - 2011/7
Y1 - 2011/7
N2 - The CMOS microchip is the workhorse of the semiconductor industry. The manufacturing model was formed with practical processing times, number of machines, steps of manufacturing process, labour cost and time required, construction costs, land costs, etc. as input parameters. This cost model attempts to analyse costs and calculate the cost per chip. Different sections of costs have been individually analysed in turn to reflect their impact on the finished product. A simulation model has been run to reflect an actual semiconductor manufacturing scenario. Simulation model is also used to estimate labour time and cost required for the process. The cost was calculated based on yield, number of chips/wafer and total expenditure by the fabrication unit. A simulation model was created in Arena 6.0 professional version, which allows the user to make changes to the model to reflect the changes in the fabrication unit.
AB - The CMOS microchip is the workhorse of the semiconductor industry. The manufacturing model was formed with practical processing times, number of machines, steps of manufacturing process, labour cost and time required, construction costs, land costs, etc. as input parameters. This cost model attempts to analyse costs and calculate the cost per chip. Different sections of costs have been individually analysed in turn to reflect their impact on the finished product. A simulation model has been run to reflect an actual semiconductor manufacturing scenario. Simulation model is also used to estimate labour time and cost required for the process. The cost was calculated based on yield, number of chips/wafer and total expenditure by the fabrication unit. A simulation model was created in Arena 6.0 professional version, which allows the user to make changes to the model to reflect the changes in the fabrication unit.
KW - Arena
KW - Cost estimation
KW - Semiconductor manufacturing
KW - Simulation
UR - http://www.scopus.com/inward/record.url?scp=79960821517&partnerID=8YFLogxK
U2 - 10.1504/IJISE.2011.041541
DO - 10.1504/IJISE.2011.041541
M3 - Article
AN - SCOPUS:79960821517
SN - 1748-5037
VL - 8
SP - 326
EP - 345
JO - International Journal of Industrial and Systems Engineering
JF - International Journal of Industrial and Systems Engineering
IS - 3
ER -