TY - GEN
T1 - Automated Air Sealing Demonstration: Denver Federal Center Building 40
AU - Iffa, Emishaw
AU - Kunwar, Niraj
AU - Salonvaara, Mikael
PY - 2023
Y1 - 2023
N2 - This project aimed to demonstrate building airtightness achieved by automated air sealing in a commercial building setting. The automated air sealing demonstrated in this project uses a modified blower door to pressurize and distribute the sealing aerosol to achieve the required building airtightness. To demonstrate this technology, Building 40 at the Denver Federal Center, a federally owned campus under the jurisdiction, custody and control of the U.S. General Services Administration (GSA), was selected for testing (Figure 2). This building is currently undergoing several retrofit projects, including increasing insulation, installing high-performance windows, and adding advanced equipment, control systems, and automated air sealing. This demonstration project involved installing automated air sealing and measuring the improvements in the building's airtightness. The automated air sealing was installed over two days by AeroBarrier, the vendor. An external blower door test contractor measured the airtightness of the demonstration space before and after air sealing. The new airtightness value and the percentage increase in airtightness were used to evaluate the energy savings potential of automated air sealing. These airtightness values were used to compute the energy savings and CO2 emissions reduction for different climate zones, building types, and initial airtightness conditions. In addition, the heating, ventilation and air conditioning (HVAC) load reduction attributable to the reduced building air leakage was studied. This study included research to determine the cost and time reduction of automated air sealing. Finally, the automated air sealing performance was evaluated qualitatively using a focus group discussion that included GSA and Bristol, the general contractor. The installation has shown the demonstration site, with a floor size of 4,462 ft2 , air leakage has reduced by more than 50% in less than 7 hours, including preparation, site sealing, and cleanup. The performance objectives were classified as quantitative or qualitative based on the evaluation metrics used to assess the project’s success. The key performance objectives for this project were the level of airtightness achieved, the time and cost required to perform the sealing, and the HVAC load reduction attributable to air sealing. Table 1 shows the quantitative performance objectives.
AB - This project aimed to demonstrate building airtightness achieved by automated air sealing in a commercial building setting. The automated air sealing demonstrated in this project uses a modified blower door to pressurize and distribute the sealing aerosol to achieve the required building airtightness. To demonstrate this technology, Building 40 at the Denver Federal Center, a federally owned campus under the jurisdiction, custody and control of the U.S. General Services Administration (GSA), was selected for testing (Figure 2). This building is currently undergoing several retrofit projects, including increasing insulation, installing high-performance windows, and adding advanced equipment, control systems, and automated air sealing. This demonstration project involved installing automated air sealing and measuring the improvements in the building's airtightness. The automated air sealing was installed over two days by AeroBarrier, the vendor. An external blower door test contractor measured the airtightness of the demonstration space before and after air sealing. The new airtightness value and the percentage increase in airtightness were used to evaluate the energy savings potential of automated air sealing. These airtightness values were used to compute the energy savings and CO2 emissions reduction for different climate zones, building types, and initial airtightness conditions. In addition, the heating, ventilation and air conditioning (HVAC) load reduction attributable to the reduced building air leakage was studied. This study included research to determine the cost and time reduction of automated air sealing. Finally, the automated air sealing performance was evaluated qualitatively using a focus group discussion that included GSA and Bristol, the general contractor. The installation has shown the demonstration site, with a floor size of 4,462 ft2 , air leakage has reduced by more than 50% in less than 7 hours, including preparation, site sealing, and cleanup. The performance objectives were classified as quantitative or qualitative based on the evaluation metrics used to assess the project’s success. The key performance objectives for this project were the level of airtightness achieved, the time and cost required to perform the sealing, and the HVAC load reduction attributable to air sealing. Table 1 shows the quantitative performance objectives.
KW - 42 ENGINEERING
U2 - 10.2172/2587500
DO - 10.2172/2587500
M3 - Technical Report
CY - United States
ER -